Water Resources Department- Schemes

A. SDRF SCHEMES 
Sl No. Name of Sub-Division Name of Scheme Estimated Amount (Rs.) AA No. with date & T.S. No. with date Physical Progress Financial Progress (Rs.) Remarks
For the Year 2019-20
1 Tezpur W.R. Sub-Division I/M for recoupment of the R/B embankment of river Belsiri at Benchimari area under SDRF for 2019-20 110.00 L AA/05_2020-21(I)_811
Dt. 09.06.2020
12% …..  Work is hampered due to rainy season
2 I/M for restoration of damages at Tengabasti on R/B embankment of river Jiabharali due to flodd under SDRF for 2019-20  250.00 L AA/05_2020-21(I)_820
Dt. 09.06.2020
6% …..  Work is hampered due to rainy season
3 I/M for restoration of damages at Bihiagaon on R/Bank embankment of river Jiabharali due to flood under SDRF for 2019-20 160.00 L AA/05_2020-21(I)_833
Dt. 10.06.2020
….. ….. Tender  under process
4 I/M for restoration of damages at Tall Kalibari area due to flood of river Brahmaputra under SDRF for 2019-20 23.00 L ….. ….. ….. SEC passed. A.A. yet not received
For the Year 2019-20
1 Chariali W.R. Sub-Division I/M for restoration of breach like damages at Bojargaon and its adjoining area by the river Jiabharali on left bank river under SDRF for the year 2019-20 160.00 L AA/05_2020-21(I)_834
Dt. 10.06.2020
….. ….. Tender  under process
For the Year 2018-19 
1 Tezpur W.R. Sub-Division I/M to protect Bangalgaon and its adjoining areas from the devastation of river Gabharu under SDRF for 2018-19 100.00 L AA/05_2020-21(I)_795
Dt. 26.05.2020
….. ….. Tender  under process
2 I/Mto protect Bihiagaon from the flood devastation of river Jiabharali on its R/B embankment under SDRF for the year2018-19 180.00 L AA/05_2020-21(I)_796
Dt. 26.05.2020
….. ….. Tender  under process
For the Year 2017-18
1 Tezpur W.R. Sub-Division I/M to protect Tinikharia area from the flood devastation of river Mansiri on its R/B under SDRF for 2017-18  197.00L  RGR.(RRR)1029/2017/69
Dt: 30.12.2017
100% Nil Scheme physically completed. Demand is placed at Revenue Department for release of fund
2 I/M to protect Kekakoli area  from the flood devastation of the river  Mansiri under SDRF for 2017-18 162.00 L RGR.(RRR)1030/2017/77
Dt: 30.12.2017
WR(EDRT)277/2012-13/177
Dt. 20.01.2018
100% Nil Scheme physically completed. Demand is placed at Revenue Department for release of fund
3 I/M for bank stabilization in Molangaon and its adjoining areas from flood devastation of river Selakathi on its right bank under SDRF for 2017-18 305.00 L RGR.(RRR)300/2018/73
Dt: 10.05.2018
WR(EDRT)277/2012-13/192
Dt. 13..09.2018
100% Nil Scheme physically completed. Demand is placed at Revenue Department for release of fund
4 I/M for bank stabilization on right bank of river Brahmaputra at New Kalibari area near Mahabhairabi Temple under SDRF for 2017-18 278.00 L RGR.(RRR)303/2018/63
Dt: 10.05.2018
100% Scheme physically completed. Demand is placed at Revenue Department for release of fund
5 I /M for restoration of flood damage at Chamdhara area by river Jiabharali under SDRF 2017-18  195.00 L  RGR.(RRR)1026/2017/62
Dt: 30.12.2017
WR(EDRT)277/2012-13/176
Dt. 20.01.2018
100% Nil Scheme physically completed. Demand is placed at Revenue Department for release of fund
6 I/M for restoration of Kahibari area from the flood devastation of river Gabharu on its right bank under SDRF for 2017-18 202.00 L RGR.(RRR)301/2018/76
Dt: 10.05.2018
100% Nil Scheme physically completed.Completion report yet to be received
For the Year 2016-17
1 Tezpur W.R. Sub-Division I/M for closing of breach at 3.40km in Besseria area on R/B of river Depota including restoration of breach like damages reaches under SDRF for 2016-17. 309.96 L RGR549/2016/31,
Dt: 19.12.2016
WR(EDRT)277/2012-13/50,
Dt. 23/12/2016
87% Nil Foreclosed "As is where is basis". Demand is  placed at Revenue Department for release of fund
(B) NABARD          
Sl No. Year Name of Scheme Estimated Amount (Rs.) AA No. with date & T.S. No. with date Physical Progress Financial Progress (Rs.) Remarks
3 NABARD RIDF XXIV Anti erosion measures to protect Berajan Rajgarh area from the flood devastation of river Jiabharali on its right bank. 200.00 L WR(ED)TECH/7/7295/2018/3
Dt.03.01.2019
100% Nil Scheme physically completed
4 NABARD RIDF XXIII Anti erosion measures to protect both bank of river Gabharu at Puthimari and Na-Beel area from the erosion of river Gabharu(Including R/S works) 400.00 L WR(C )487/2017/05
Dt. 18.11.17
WR(ED)Tech/7069/2017/6
Dt.05.12.2017
100% 302.36503 L work physically  completed
5 Protection of left bank of river Jiabharali at upstream of NH-52. 450.00 L WR(C )490/2017/05
Dt. 22.11.2017
100% 383.290 L work physically  completed

 

C. SOPD (G) SCHEMES
Sl No. Name of Scheme Estimated Amount(Rs.) AA No. with date & T.S. No. with date Physical Progress Financial Progress (Rs.) Remarks
 Tezpur W.R. Sub-Division
1 A/E measures to protect Berajan Rajgarh area from the flood devastation of river Jiabharali on its R/B under SOPD for 2019-20 350.00 L AA/FC_2019-20(l)_581
Dt. 18.01.2020
12% Nil Work is hampered due to rainy season
D. CMRF SCHEMES
Sl No. Year Name of Scheme Estimated Amount (Rs.) AA No. with date & T.S. No. with date Physical Progress Financial Progress Remarks
4 2018-19 Protection of Louguti L.P. School and its adjoining areas  from the erosion of river Brahmaputra for 2018-19 Rs.18.23 L CMS (A)13/2018/169, Dtd. 30.06.2018
SEN/TS/170/Pt-II/1994/267
Dtd. 06.08.2018
100% Nil Demand placed at Revenue Department

 

(E) FMP SCHEMES          
Sl No. Name of Scheme Estimated Amount (Rs.) AA No. with date & T.S. No. with date Physical Progress Financial Progress (Rs.) Remarks
1 Protection of Tezpur University and its adjoining areas from the erosion of river Jia-Bharali. 23.18 Cr WR(C )257/2013/22
Dt. 04.12.2014
WR(ED)Tech/6140/2012/14
Dt. 12.01.2015
79.80% 1506.70 L Foreclosed "As is where is basis"
2 Protection of Biswanath Panpur including areas of upstream Silamari and far downstream Bhumuraguri to Borgaon against erosion of the river Brahmaputra. 167.09 Cr WR(C )162/2011/25
Dt. 21.11.2014
WR(ED)Tech/6121/2011/19
Dt. 17.01.2014
77.28% 7518.870 L Foreclosed "As is where is basis"
3 Protection of T-Dyke from Chillanipam to Orangbasti from the erosion of river Jia-Bharali on its left bank. 13.6460 Cr. WR(C )166/2011/22
Dt. 22.10.2014
WR(ED)Tech/6112/11/15
Dt. 12.01.2015
69.76% 375.63 L Foreclosed "As is where is basis"

 

F. DEPOSIT WORK (ARMY)          
             
  Name of Scheme Estimated Amount (Rs.) AA No. with date & T.S. No. with date Physical Progress Financial Progress (Rs.) Remarks
1 A/E measures of river Ghabharu to protect Army Cantonment area at Missamari 3359.17 L MoD, GOI Approval
2010/PM-2/81/E2
Dt. 16.11.2015
WR(ED)Tech/6547/1515/4
Dt. 19.12.2015
100% 3057.99210 L Work physically completed