State Govt. Sponsored Schemes |
|||||||
STATE OWN PRIORITY DEVELOPMENT SOPD - FDR FOR 2019-20 |
|||||||
Signature Project : SOPD(G) |
|||||||
Dist : SONITPUR |
|||||||
Name of the Department : PWD Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli |
|||||||
Sl No. |
Name of Scheme |
Length in KM |
|
|
Remarks |
||
Tender amount |
Date of Work Order issue and Contractor's details |
Physical achievement |
|||||
Progress |
|||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
|
1 |
Improvement & Widening of Road from NH-15 at Sirajuli to Barchalla under SOPD(G) (Signature Project) for the year 2019-20 under Barchalla LAC under Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli. |
9.00 |
999.93 |
M/S Prabhu Agarwalla const. Pvt.Ltd |
20% |
Work in progress |
|
2 |
Improvement of Dhekiajuli to Dhekiajuli Railway Station Road under SOPD (G) Signature Project for the year 2019-20 |
9.00 |
999.99 |
Anil Das |
60% |
Work in progress |
Centrally Sponsored Scheme: |
||||||||||
Statement showing the monthly progress report of PMGSY (Regular), PMGSY (ADB) under , Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli |
||||||||||
District :- Sonitpur |
|
|||||||||
Division.:- Barchalla & Dhekiajuli Territorial Road Division |
|
|||||||||
Sl. No. |
Package No. |
Tender Value in Rs.(lakh) |
Name of Contractors |
Name of road |
Name of Sub-Div. |
Proposed work, Road in Km / |
Progress |
Remarks |
||
Physical in % |
||||||||||
Road Part |
Br. Part |
|||||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
|
PMGSY (Batch-I) 2017-18 |
||||||||||
1 |
AS-22-175 |
90.00 |
M/s Bharvika Infrastructure |
Ghogra to Dhirai T.E. |
Dhekiajuli |
1.342 |
|
100% |
|
Work completed |
2 |
AS-22-176 |
53.11 |
Nuruddin Ahmed Pathan |
NH-52 to Gorbasti |
Dhekiajuli |
0.816 |
|
100% |
|
Work completed |
3 |
AS-22-177 |
179.86 |
Bichitra Basumatary |
Saikia Chuburi to NH-52 |
Dhekiajuli |
1.560 |
|
100% |
|
Work completed |
4 |
AS-22-178 |
140.82 |
Parimal Saikia |
Thelamora to Kamar Pathar |
Dhekiajuli |
2.068 |
|
100% |
|
Work completed |
5 |
AS-22-179 |
72.15 |
Debojit Borah |
Kalakuchi to Bahbera Ka L38 |
Dhekiajuli |
1.200 |
|
100% |
|
Work completed |
6 |
AS-22-180 |
352.24 |
Mousum Bora |
Hugrajuli TE No.1 to Narenkati |
Dhekiajuli |
3.697 |
|
100% |
100% |
Work completed |
7 |
AS-22-181 |
243.67 |
Lalit Kr. Agarwala |
Gormara to Gangapur |
Dhekiajuli |
3.134 |
|
100% |
|
|
8 |
AS-22-182 |
359.19 |
Deepak Busha |
Ulubari to Bamun Pukhuri |
Dhekiajuli |
5.139 |
|
100% |
|
Work completed |
9 |
AS-22-183 |
256.02 |
Surjya Das |
Mazrowmari Kachari to Gohain Ali |
Dhekiajuli |
3.390 |
|
97% |
|
Work in progress |
10 |
AS-22-184 |
221.66 |
Bichitra Basumatary |
Amtol Bhergaon to Gohaibheti L 52 |
Dhekiajuli |
4.375 |
|
100% |
|
Work completed |
11 |
AS-22-185 |
140.340 |
Girindra Kr. Bhuyan |
Borbil Kachari to Ghotua, L27 |
Dhekiajuli |
2.345 |
|
100% |
|
Work completed |
12 |
AS-22-187 |
96.660 |
Nuruddin Ahmed Pathan |
Kachari gaon to Ulubari No1, L25 |
Dhekiajuli |
1.630 |
|
100% |
|
Work completed |
13 |
AS-22-188 |
186.660 |
Girindra Kr. Bhuyan |
Senimari to Ghogra Borpeta |
Dhekiajuli |
2.945 |
|
100% |
|
Work completed |
14 |
AS-22-189 |
121.83 |
Parimal Saikia |
Borbil to Dhekipeluwa Kachari |
Dhekiajuli |
1.455 |
|
100% |
|
Work completed |
15 |
AS-22-190 |
317.57 |
Bichitra Basumatary |
Belsiri Rly Station to Sessabil |
Dhekiajuli |
3.656 |
|
100% |
|
Work completed |
16 |
AS-22-191 |
134.230 |
Deepak Busha |
Ulubari to Meghai Ati, L066 |
Dhekiajuli |
2.340 |
|
100% |
|
Work completed |
17 |
AS-22-192 |
314.750 |
Mousum Bora |
Sopai TE to Akabil, L077 |
Dhekiajuli |
4.768 |
|
100% |
|
Work completed |
18 |
AS-22-193 |
535.44 |
Girindra Kr. Bhuyan |
Joseph Line to Akabil |
Dhekiajuli |
4.958 |
|
100% |
100% |
Work completed |
19 |
AS-22-194 |
109.470 |
Parimal Saikia |
Dhankhanda to Bandarhagi, L064 |
Dhekiajuli |
1.739 |
|
100% |
|
Work completed |
20 |
AS-22-196 |
274.61 |
Kulen Hazarika |
Garubandha to Dighaldal, |
Dhekiajuli |
4.282 |
|
100% |
|
Work completed |
21 |
AS-22-197 |
123.30 |
Suraj Basumatary |
Chariali Ka to Bhutia Ali |
Dhekiajuli |
1.741 |
|
100% |
|
Work completed |
22 |
AS-22-198 |
444.08 |
M/s Bharvika Infrastructure |
Sopai Baligaon No.2 to Rakyasmari |
Dhekiajuli |
2.628 |
|
95% |
80% |
Work in progress |
23 |
AS-22-199 |
141.17 |
Deepak Busha |
Amtolbaligaon to Mazbaligaon |
Dhekiajuli |
1.657 |
|
100% |
|
Work completed |
24 |
AS-22-200 |
254.75 |
Debojit Borah |
Dhankhanda to Bandarhagi, L065 |
Dhekiajuli |
3.388 |
|
100% |
|
Work completed |
25 |
AS-22-201 |
98.38 |
Nuruddin Ahmed Pathan |
Thelamora to Arasuti |
Dhekiajuli |
1.615 |
|
100% |
|
Work completed |
26 |
AS-22-202 |
315.79 |
Deepak Busha |
Rakyashmari to Sopai Jhargaon |
Dhekiajuli |
3.270 |
|
100% |
|
Work completed |
27 |
AS-22-203 |
128.87 |
Khem Sarma |
Bhangamandir to Karhana gaon |
Barchalla |
2.215 |
|
100% |
|
Work completed |
28 |
AS-22-204 |
137.82 |
Surjya Das |
Arun Bagan No.4 to Singri |
Barchalla |
2.577 |
|
100% |
|
Work completed |
29 |
AS-22-205 |
285.690 |
Nuruddin Ahmed Pathan |
Nurpurjuli No.2 to Singri |
Barchalla |
5.397 |
|
100% |
|
Work completed |
30 |
AS-22-206 |
50.42 |
Saugat Dey |
Bairaguri Pathar to Bairaguri Bengaligaon L39 |
Barchalla |
0.872 |
|
100% |
|
Work completed |
31 |
AS-22-207 |
129.23 |
Surjya Das |
Balijan to Natun Jamuguri |
Barchalla |
1.973 |
|
100% |
|
Work completed |
32 |
AS-22-208 |
195.380 |
Surjya Das |
Borchola to Dalbari , L047 |
Barchalla |
3.356 |
|
100% |
_ |
Work completed |
PMGSY 2018-19 |
|
|
|
|
|
|
||||
1 |
AS-22-195 |
155.52 |
M/s Bharvika |
Sanmilani to Charali Kha |
Dhekiajuli |
1.776 |
|
100% |
|
Work completed |
2 |
AS-22-302 |
83.77 |
Biman Choudhury |
Keherukunda Pathar to NH-52 |
Barchalla |
1.520 |
|
100% |
|
Work completed |
3 |
AS-22-309 |
120.47 |
Surjya Das |
Kathaudubba to Gormora PWD Rd. |
Dhekiajuli |
1.610 |
|
100% |
|
Work completed |
4 |
AS-22-315 |
187.66 |
Parimal Saikia |
Nagapathar to Dhankhanda |
Dhekiajuli |
2.810 |
|
100% |
|
Work completed |
PMGSY -II 2019-20 |
|
|
|
|
|
|
||||
1 |
AS-22-645 |
752.45 |
Sri Nirmal Pathak |
MRL04-Palash Pathar to Singri bagan No.5 |
Barchalla |
11.00 |
50.76 |
5% |
|
Work in progress |
2 |
AS-22-646 |
954.98 |
Sri Nirmal Pathak |
MRL02-NH 15 to Singri Bagan |
Barchalla |
13.42 |
|
10% |
|
Work in progress |
3 |
AS-22-648 |
1085.43 |
Prabhu Agarwalla Const. Pvt. Ltd. |
MRL01-Bhotpara to Sopai Tea |
Dhekiajuli |
15.21 |
19.40 |
15% |
|
Work in progress |
4 |
AS-22-649 |
1574.85 |
Prabhu Agarwalla Const. Pvt. Ltd. |
MRL02-Keherukhanda to Nagapathar |
Dhekiajuli |
14.13 |
|
40% |
|
Work in progress |
State Govt. Sponsored Schemes |
||||||
Annual Plan (Development of Specific Road) |
|
|
|
|||
Dist : SONITPUR |
|
|
|
|
|
|
Name of the Department : PWRD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli |
||||||
Sl No. |
Name of Scheme |
Length in km |
Tender amount |
Date of Work Order issue and Contractor's details |
Physical |
Remarks |
|
||||||
Progress |
||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
Improvement of Road by Providing C.C Block from Habinamghor to Puthimari link PWD Road via Gopinath Bordoloi M.V School, Balisuti, Triveni chowk,Kaibartagaon and Dhakalgaon and Bihari Basti Borogaon under Development of Specific Road(A.P) for the year 2015-16 under Sonitpur Rural Road Division. |
11.00 |
752.831 |
CE/DEV/TB/368/2015-16/14 Dtd.12/11/2017 ,M/s Prabhu Agarwalla Construction Pvt. Ltd. ,Mangaldoi,Darrang |
93% |
Work in progress |
Centrally Sponsored Scheme: |
||||||||
RIDF Schemes -XXIII |
||||||||
Dist : SONITPUR |
|
|
|
|
|
|
||
Name of the Division :- Barchalla & Dhekiajuli Territorial Road Division |
|
|
||||||
Sl No. |
Name of Scheme |
Length in KM |
Bridge |
Tender amount Rs in Lakh |
Date of Work Order issue and Contractor's details |
Physical Progress |
Remarks |
|
1 |
2 |
3 |
|
4 |
5 |
6 |
7 |
|
1 |
Constn. of RCC Br. No.1/1 on Jungle Basti Road including approaches & protection works under RIDF-XXIII of NABARD Pkg. No. Sonit/RIDF-XXIII/02 |
|
1No. |
81.14 |
Sri Girindra Kr Bhuyan CE/DEV/RIDF-XXIII/213/2017-18/6, Dtd. 27/11/2017 |
100% |
Work Completed |
|
2 |
Construction of RCC Bridge No 1/3 on Narayankati Rowmari via Gerua Juli Road including approaches & protection works under RIDF-XXIII of NABARD |
|
1 No. |
116.496 |
Sri Rajendra Choudhury CE/DEV/RIDF-XXIII/214/17-18/6 Dtd. 18/12/2017 |
100% |
Work Completed |
|
3 |
Construction of Road by Paver Block from Bhergaon to Natun Pam via Bhairaguri (Ch.0.00 M to Ch. 3900.00M) under RIDF-XXII of NABARD for the year 2016-17. Package No. SONITPUR/RIDF-XXII/05. |
3.900 |
|
296.606 |
Sri Pabitra Boro |
100% |
Work completed |
|
4 |
Constn. of RCC Br. No.3/1 on Borchalla Photasimalu Road including approaches & protection works under RIDF-XXIII of NABARD Pkg. No. Sonit/RIDF-XXIII/06 |
|
1 No. |
396.26 |
M/s Prabhu Agarwalla |
92% |
Work in progress |
MAHABIR LACHIT CHILARAI SETU NIRMAN ABHIJAN UNDER SOPD-G & RIDF OF NABARD |
||||||
Dist : SONITPUR |
||||||
Name of Division:- Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli |
||||||
|
|
|
|
|
||
Sl.No |
Name of Work |
AA No & date |
Name of contractor |
Contract amount Rs in L |
Physical progress |
Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
State Govt. Sponsored Schemes |
||||||
MAHABIR LACHIT CHILARAI SETU NIRMAN ABHIJAN UNDER SOPD-G FOR 2018-19 |
|
|
|
|
||
1 |
Construction of RCC Br.No.2/1 on Hugrajuli Rakhasmari road via Bhelaguri including approaches & protection work under MLCSNA under SOPD-G for the year 2018-19. (Package No.MLCSNA/SOPD(G)/Dhekiajuli-01) |
AA/PWR_2018-19_(I)_10168,dtd.30/01/19 |
Deepak Kr. Bucha |
376.48672 |
55% |
Work in Progress |
2 |
Construction of RCC Br.No.1/2 on Batasipur to Monabagh including approaches & protection work under MLCSNA under SOPD-G for the year 2018-19. |
|
Deepak Kr. Bucha |
292.11000 |
20% |
Work in Progress |
3 |
Construction of RCC Br.No.1/1 on Dhekiajuli Rly Station to Aboi Centre including approaches & protection work under MLCSNA under SOPD-G for the year 2018-19. |
CESTBR/MLCSNA/SOPD(G)/48/2018-19/3 DT.03.10.2019 |
Lalit Kr. Agarwala |
332.65000 |
70% |
Work in Progress |
4 |
Construction of RCC Bridge under Mahabir Lachit -Chilarai Setu Nirman Abhijan under SOPD (G) for the year 2018-19. (Package No.MLCSNA/SOPD(G)/BARCHALLA/01) (i)RCC bridge No 2/1 on Barchalla To Nisalamari |
AA/PWR_2019-20_(I)_34339,dtd.23/01/2020 |
Nirmal Pathak |
577.65600 |
90% |
Work in Progress |
(ii)RCC bridge No 2/1 on Kalita gaon to Butibora Chuburi and |
90% |
Work in Progress |
||||
(iii)RCC bridge No 2/1 on Makhowajan to Amguri Kachari road including approaches and protection work. |
90% |
Work in Progress |
||||
Centrally Sponsored Scheme: |
||||||
MAHABIR LACHIT CHILARAI SETU NIRMAN ABHIJAN UNDER RIDF-XXIV OF NABARD FOR 2018-19 |
|
|
|
|
||
1 |
(i) Construction of RCC Br.No.2/1 on Nepali Basti Naharani road Berbhari Kathalguri road & (2) Constn.of RCC Bridge No.4/2 with approaches on Santipur to Pub-Gangapur via Thakurbasti under MLCSNA under RIDF-XXIV of NABARD for the year 2018-19 under Sonitpur State Road Division under Dhekiajuli LAC, Package No..MLCSNA/Sonitpur/05 |
AA/PWR_2018-19_(I)_9534,dtd.29/12/18 |
Nirmal Pathak |
381.95100 |
45% |
Work in Progress |
2 |
(i) Construction of RCC Br.No.123/1 on Thelamora Chagaliahat road under MLCSNA under RIDF-XXIV of NABARD for the year 2018-19 under Sonitpur State Road Division under Dhekiajuli LAC, Package No..MLCSNA/Sonitpur/02 |
AA/PWR_2018-19_(I)_5489,dtd.29/12/18 |
Prabhu Agarwalla |
976.76142 |
15% |
Work in Progress |
3 |
Construction of RCC bridge no. 3/1 on Dhiraimajuli to Singri Kalisthan road including approaches and protection work under Mahabir Lachit -Chilarai Setu Nirman Abhijan under RIDF-XXIV of NABARD for 2018-19. |
AA/PWR_2018-19_(I)_5490,dtd.29/12/18 |
Nirmal Pathak |
389.78100 |
50% |
Work in Progress |
MAHABIR LACHIT CHILARAI SETU NIRMAN ABHIJAN UNDER RIDF-XXV OF NABARD FOR 2019-20 |
|
|
||||
1 |
Construction of RCC Br. No.2/1 on Balisuti (Khelmati) to Murhabasti under Mahavir Lachit Chilarai Setu Nirman Abhijan (MLCSNA) under RIDF-XXV of NABARD for 2019-20 (LAC Barchalla) Pkg. No. MLCSNA/RIDF-XXV/Sonitpur/05 |
AA/PWR_2020-21_(I)_37421,dtd.20.06.2020 |
Mousum Bora |
#REF! |
85% |
Work in Progress |
2 |
Construction of RCC Br. No.1/4 on Sanmilani Chariali to Bhutia Ali Road including approaches and protection works under RIDF-XXV of NABARD for 2019-20 (LAC Dhakiajuli) Pkg. No. MLCSNA/RIDF-XXV/Sonitpur/08. |
AA/PWR_2019-20_(I)_34636,dtd.04.02.2020 |
Mousum Bora |
#REF! |
75% |
Work in Progress |
3 |
Construction of RCC Br. No.2/1 on Barson Ghagra to Niz Bahabari under Mahavir Lachit Chilarai Setu Nirman Abhijan (MLCSNA) under RIDF-XXV of NABARD for 2019-20 (LAC Barchalla) Pkg. No. MLCSNA/RIDF-XXV/Sonitpur/06. |
AA/PWR_2019-20_(I)_34639,dtd.04.02.2020 |
Prasanta Dey |
#REF! |
2% |
Work in Progress |
State Govt. Sponsored Schemes |
|
|||||||
STATE OWN PRIORITY DEVELOPMENT (SOPD - G) |
|
|||||||
|
||||||||
Dist : SONITPUR |
|
|||||||
Name of Division:- Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli |
|
|||||||
Sl.No |
Name of Work |
Name of contractor |
Contract amount Rs in L |
Physical progress |
Remarks |
|||
1 |
2 |
3 |
4 |
5 |
6 |
|||
|
STATE OWN PRIORITY DEVELOPMENT (SOPD - G) for 2017-18 |
|
|
|
|
|||
1 |
Construction of Road from Bhotpara Chowk to Narayanpur Lakhmi Narayan Mandir(ch. 0.00m to ch. 2500.00m) under SOPD-G for the year 2017-18 |
Sri Deepak Kumar Bucha CE's W/o No.ACE/T/CS/190/95/Pt.I/95 Dtd.22/01/2018 |
165.96 |
100% |
Work Completed |
|||
2 |
Construction of Road from Narayanpur to Rakshmari (Ch.0.00m to Ch.10500.00m) under SOPD(G) for the year 2017-18 |
M/S Bass Farum |
698.07 |
100% |
Work Completed |
|||
3 |
Construction of Road from NH-15 at Kawoimari to Bamunpukhuri (Ch.0.00m to Ch.3000.00m) under SOPD(G) for the year 2017-18. Package No.Dhekiajuli/SOPD(G)/02. |
Sri Deepak Kumar Bucha, CE's W/o No.CE/DEV/TB/278-Pt.I/2017-18/5 Dtd.05/02/2018 |
268.12 |
95% |
Work in Progress |
|||
4 |
Construction of Road from Naharbari to Kholohubari(Ch.0.00m to Ch.4500.00m) under SOPD(G) for the year 2017-18 |
Sri Deepak Kumar Bucha, CE/DEV/TB/278/Pt-IV/2017-18/7 |
319.99 |
60% |
Work in Progress |
|||
5 |
Construction of Martyrs Tomb (Swahid Bedi) under SOPD (G) for 2017-18= 13 Nos. |
Manoj Talukder |
129.22 |
100% |
Work completed |
|||
STATE OWN PRIORITY DEVELOPMENT (SOPD - G) for 2018-19 |
|
|
|
|
||||
1 |
Improvement of NH-15 to Thelamara High School under SOPD-G for the year 2018-19 under Sonitpur State Road Division. |
10/01/19, Sundiya Goyari,Dhekiajuli |
23.47386 |
100% |
Work completed |
|||
2 |
Improvement of road from NH-15 bye lane towards North near Thakurbari Tample under SOPD-G for the year 2018-19 under Sonitpur State road Road Division. |
10/01/19, Manoj Mahali |
12.77996 |
100% |
Work completed |
|||
3 |
Improvement of Dayal Panika road & bye lane -I towards north under SOPD-G for the year 2018-19 under Sonitpur State road Road Division. |
10/01/19, Bharvika Infrastructure |
41.37000 |
100% |
Work completed |
|||
4 |
(i)Impvt.of Kawaimari to Borbil Kachari road under SOPD-G for the year 2018-19 |
Prabhu Agarwalla Constn.Pvt. Ltd. |
450.21 |
100% |
Work completed |
|||
(ii)Impvt.of road from Gadhajuli to Belsiri Railway Station road under SOPD-G for the year 2018-19 |
||||||||
(iii)Impvt.of road from Gadhajuli to Belsiri Railway Station road under SOPD-G for the year 2018-19 (from ch.6000.00m to ch.14150.00m) |
||||||||
5 |
(i)Impvt.of Road from 109th Km of NH-15 to to Belsiri Railway Station under SOPD-G for the year 2018-19 |
Prabhu Agarwalla Constn.Pvt. Ltd. |
428.02 |
100% |
Work completed |
|||
(ii)Impvt.of Garubandha Kalamati Gate under SOPD-G for the year 2018-19 |
||||||||
(iii)Impvt.of road from Nabil to Dhankhanda road under SOPD-G for the year 2018-19 |
||||||||
6 |
Impvt.of Julia to Akabil road under SOPD-G for the year 2018-19 |
Deepak Kr.Bucha |
119.14400 |
60% |
Work in Progress |
|||
7 |
Impvt.of Batasipur St.Antony School road under SOPD-G for the year 2018-19 |
Deepak Kr.Bucha |
149.52800 |
100% |
Work cmpleted |
|||
8 |
(i)Impvt.of NH-15 to Tinkharia TE (PMGSY) under SOPD-G for the year 2018-19 |
Prabhu Agarwalla Constn.Pvt. Ltd. |
332.84 |
100% |
Work completed |
|||
(ii)Impvt. Of Santipara to Monmohinipur road (PMGSY) under SOPD-G for the year 2018-19 |
||||||||
(iii)Impvt.of Hirajuli TE to Gorjuli road (PMGSY) under SOPD-G for the year 2018-19 |
||||||||
(iv)Impvt.of Gormara Pathar road under SOPD-G for the year 2018-19 |
||||||||
(v)Impvt.of Gormara to Gorjuli road under SOPD-G for the year 2018-19 |
||||||||
(vi)Impvt.of Ghagra Kachari to Panchnoi under SOPD-G for the year 2018-19 |
||||||||
9 |
Improvement of Road from Sirajuli Satra to Pirakata via Bondaijharoni Center under SOPD-G for the year 2018-19 Package No BARCHALLA/SOPD-G/2018-19/03 |
Samim Pathak |
313.0155 |
97% |
Work in Progress |
|||
10 |
Construction of Road from NH-15to Borgaon Centre Link Road via Borgaon Chapori & 2 Chengahiloi to Garuduba Link Road under SOPD-G for the year 2018-19 Package No BARCHALLA/SOPD-G/2018-19/04 |
Manoj Talukder |
297.1665 |
95% |
Work in Progress |
|||
11 |
Construction of Road from 1 Doomdoma Bidyapeeth to Singimari Bengali gaon 2. Singimari Boro gaon Road 3. Barjhar to Bam Goroimari Link Road 4.Singri Kalisthan to Polo Star Academy & 5. Bhangamandir to Balijan Kochari via Pub-Bhangamandir LP School under SOPD-G for the year 2018-19 Package No BARCHALLA/SOPD-G/2018-19/05 |
Nirmal Pathak |
467.3 |
100% |
Work completed |
|||
12 |
Construction of Road from 1 Bandamari Centre to Ghagra Kochari (L=2.00 Km) 2. Khelmati Centre to Patrapara Kishan Basti via Khusurabari Orang gaon Road (L= 2.00 Km)& 3. Tamulbari to Soroka Baligaon Road (L= 2.10 Km) under SOPD-G for the year 2018-19 Package No BARCHALLA/SOPD-G/2018-19/02 |
Nirmal Pathak |
431.7885 |
92% |
Work in Progress |
|||
13 |
Imp/Construction of PWD Roads (1) Binduguri Bandamari Road (Ghogra T.E. to Tumuki Road)(L= 4.8Km) (2) Ghogra TE to Tumuki Road(Tumuki to Tamulbari Road)(L= 2.5Km) (3) Gundurahil to Niz Bahbari Road (Chingachuburi to Ghogra RCC Br. Via Bahbari Chariali)(L= 3 Km) (4) Patipukhuri to Erasuti Jungle Road (Johamari Teliagaon Road)(L= 1.7Km) (5) Barchalla Photasimalu Road.(L= 1.7 Km) (6) Bhalukdhara Bagoribari Road(L = 2.0Km) under SOPD-G for the year 2018-19 Package No BARCHALLA/SOPD-G/2018-19/01 |
Surjya Das |
327.843 |
17% |
Work in Progress |
|||
14 |
Construction of Road from Balisia Kochari to Ghanshyam Centre under SOPD-(G) for the year 2018-19 Barchalla LAC Package No TRC/SOPD-G/RE/BOR/03 |
Sri Kumar Ravi Jaiswal |
159.42 |
95% |
Work in Progress |
|||
STATE OWN PRIORITY DEVELOPMENT (SOPD - G) for 2019-20 |
|
|
|
|
||||
1 |
Re-construction of Office Bldg. with Sanitary works, approach road, Installation of furniture to the office of Asstt. Executive Engineer Dhekiajuli Territorial road Sub division under SOPD-G for the year 2019-20 District- Sonitpur (Assam), Dhekiajuli LAC |
Mandeep Singh |
25.11 |
45% |
Work in Progress |
|||
2 |
Re-construction of Kalakuchi to Ulubari - 2 road under SOPD-G for the year 2019-20, Dhekiajuli LAC |
Rinku Nath |
21.83 |
5% |
Work in Progress |
|||
3 |
Re-construction of Surjyapur No - 2 to NH 15 road under SOPD-G for the year 2019-20, Dhekiajuli LAC |
Nabajyoti Baishya |
23.15 |
|
Work in Progress |
|||
4 |
Re-construction of NH-15 to Tinkharia TE (remaining portion) road under SOPD-G for the year 2019-20, Dhekiajuli LAC |
M/S Agnigarh |
25.11 |
5% |
Work in Progress |
|||
5 |
Re-construction of Hirajuli to Gorjuli road under SOPD-G for the year 2019-20, Dhekiajuli LAC |
Rinku Nath |
64.86 |
10% |
Work in Progress |
|||
6 |
Re-construction of Rakyasmari to Samarajuli road under SOPD-G for the year 2019-20, Dhekiajuli LAC |
Suraj Kr. Basumatary |
70.50 |
100% |
Work completed |
|||
7 |
Re-construction of NH 15 to Belsiri Rly Station (remaining portion) road under SOPD-G for the year 2019-20, Dhekiajuli LAC |
M/S Priyashi Ashi Developer (P) Ltd. |
204.47 |
5% |
Work in Progress |
|||
8 |
Re-construction of Mazrowmari to Hoograjuli Rly Station road under SOPD-G for the year 2019-20, Dhekiajuli LAC |
M/S Priyashi Ashi Developer (P) Ltd. |
264.96 |
10% |
Work in Progress |
|||
9 |
Re-construction of Gogra Kachari to Panchnoi Nepali road (Ch 2200.00 to 16550.00 m) (remaining portion) under SOPD-G for the year 2019-20, Dhekiajuli LAC |
Sunil Kr. Verma |
298.67 |
30% |
Work in Progress |
|||
10 |
Construction of road from near Hari Har Mandhir to Nepaligaon ( from Ch 0.00 to 1300.00 m) under SOPD-G for the year 2019-20 of Barchalla & Dhekuajuli Territorial road division Dhekiajuli LAC No. 71, Dhekiajuli LAC |
Deepak Kr.Bucha |
|
|
Work in Progress |
|||
11 |
Construction of road from Mitham to Panbari road ( from Ch 0.00 to 1100.00 m) under SOPD-G for the year 2019-20 of Barchalla & Dhekuajuli Territorial road division Dhekiajuli LAC No. 71, Dhekiajuli LAC |
Kumar Ravi Jaiswal |
89.70 |
10% |
Work in Progress |
|||
12 |
Construction of road from Nepali Basti to Naharoni ( from Ch 0.00 to 3800.00 m) under SOPD-G for the year 2019-20, Dhekiajuli LAC |
Manoj Talukder |
|
15% |
Work in Progress |
|||
13 |
Construction of road from Pakoriguri to Belsiri ( from Ch 0.00 to 2500.00 m) under SOPD-G for the year 2019-20, Dhekiajuli LAC |
Mousam Bora |
215.35 |
25% |
Work in Progress |
|||
14 |
Construction of road from Gangapur to Shantipur ( from Ch 0.00 to 2250.00 m) under SOPD-G for the year 2019-20, Dhekiajuli LAC |
|
|
|
Under Tender process |
|||
15 |
Re-construction Of Office Compound of the office of the Asstt. Executive Engineer, Barchalla Territorial Road Sub-Division under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli,Dist. - Sonitpur (Assam), Barchalla LAC |
M/S Balaji Commercial |
49.13 |
20% |
Work in Progress |
|||
16 |
Re-construction of Borjhar to Balijan Kachari Road of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli, Barchalla LAC |
Md. Alaluddin |
95.83 |
30% |
Work in Progress |
|||
17 |
Re-construction of NH-15 to Rangagara road (S.D.B.C. Patch repair etc.) under SOPD-G for the year 2019-20 in PWD Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli (Length= 5.00 km), Barchalla LAC |
Sanjay Kr. Agarwalla |
98.08 |
5% |
Work in Progress |
|||
18 |
Re-construction of Keherukhanda Pather - NH-15 road (S.D.B.C. Patch repair etc.) under SOPD-G for the year 2019-20 in PWD Barchalla & Dhekiajuli Road Division, Dhekiajuli (Length= 1.50 km), Barchalla LAC |
Om Prakash Sarma |
28.92 |
2% |
Work in Progress |
|||
19 |
Re-construction of Pithakhuwa to Likhokgaon road (S.D.B.C, Patch repair etc.) under SOPD-G for the year 2019-20 in PWD Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli (Length= 0.50 km), Barchalla LAC |
Kumar Rabi Jaishawal |
9.01 |
|
Work in Progress |
|||
20 |
Re-construction of Bihaguri Daily Bazar to Likhokgaon via. Katakichuburi road (S.D.B.C, Patch repair etc.) under SOPD-G for the year 2019-20 in PWD Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli (Length= 1.10 km), Barchalla LAC |
Kumar Rabi Jaishawal |
16.93 |
|
Work in Progress |
|||
21 |
Re-construction of Singri Chitalmari road (S.D.B.C, Patch repair etc.) under SOPD-G for the year 2019-20 in PWD Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli (Length= 3.00 km ), Barchalla LAC |
Jiban Pathak |
60.07 |
|
Work in Progress |
|||
22 |
Re-construction of Kawoimari Tiniali to Teliagaon Road (Ch. 8100m to Ch. 9850m) of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli, Barchalla LAC |
Lalit Kalita |
54.81 |
35% |
Work in Progress |
|||
23 |
Re-construction of Khelmati Centre to Balisuti Road of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli, Barchalla LAC |
Ranjit Mech |
33.24 |
5% |
Work in Progress |
|||
24 |
Re-construction of road from NH-15 at Rabartola to Bhangamandir of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli, Barchalla LAC |
Sunil Kr. Verma |
227.62 |
5% |
Work in Progress |
|||
25 |
Re-construction of road from NH-15 at Chagaliahat to Khelmati of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli, Barchalla LAC |
Sunil Kr. Verma |
243.46 |
100% |
Work Completed |
|||
26 |
Re-construction of Habigaon to Borson Ghogra Road of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli, Barchalla LAC |
Tuloshi Kr. Borah |
82.67 |
7% |
Work in Progress |
|||
27 |
Improvement of Dherai Majuli Sutipathar Link Road via Chubb Gaon of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Teritorial Road Division, Barchalla LAC |
Kabendra Deka |
93.23 |
|
Work in Progress |
|||
28 |
Improvement of Pub Borgaon GP to No. 2 Borpukhuri Road (Ch. 240 m to Ch. 1140 m) of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli, Barchalla LAC |
Md. Alaluddin |
64.98 |
15% |
Under Tender process |
|||
29 |
Improvement of Road from Kachari Balijan to Pub-Bhanga Mandir of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Teritorial Road Division, Barchalla LAC |
Suraj Kr. Basumatary |
159.71 |
60% |
Work in Progress |
|||
30 |
Improvement of road from Rajuwarbasti to Kaliagohain Than of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli, Barchalla LAC |
Rajib Rabha |
133.02 |
35% |
Work in Progress |
|||
31 |
Improvement of road from Habigaon to Borghop via Majorhola of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Barchalla LAC |
M/S Amina Enterprise |
141.92 |
45% |
Work in Progress |
|||
32 |
Improvement of road from Tripurari Chowk to NH-15 via Arasuti Jungle of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli, Barchalla LAC |
|
125.22 |
|
Under Tender process |
|||
33 |
Improvement of Silpota Dumduma via Duttabasti Road of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli, Barchalla LAC |
Monoj Talukdar |
114.94 |
53% |
Work in Progress |
|||
34 |
Improvement of road from Niz Barchalla Library to Dasgaon via Kochgaon of Barchalla LAC under SOPD-G for the year 2019-20 under PWD, Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli, Barchalla LAC |
Monoj Talukdar |
167.01 |
10% |
Work in Progress |
|||
State Govt. Sponsored Schemes |
|||||||
ASSAM ROAD MAINTENANCE FUND |
|||||||
Name of the Department : PWD Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli |
|||||||
Dist : SONITPUR |
|||||||
Sl No. |
Name of Scheme |
Length in KM |
Tender amount |
Date of Work Order issue and Contractor's details |
Physical Progress |
Remarks |
|
1 |
2 |
3 |
6 |
7 |
14 |
17 |
|
1 |
Construction of proposed two storied RCC (Ground Floor RCC + First Floor Assam Type) New PWD Inspection Bunglow at Dhekiajuli under Assam Road Maintenance Fund for the year 2017-18. |
|
148.332 |
Aditya Das |
65% |
Work in progress |
|
State Govt. Sponsored Schemes |
|||||
|
Conversion of 1000 Nos of Timber Bridges into RCC Bridges |
|||||
|
Dist : SONITPUR |
|
|
|
|
|
|
Name of Division:- Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli |
|
|
|
|
|
|
|
|
Tender amount |
Date of Work Order issue and Contractor's details |
Physical Progress |
Remarks |
|
||||||
|
1 |
2 |
3 |
4 |
5 |
6 |
|
1 |
Construction of RCC BR. No. 1/1 over River Julia on Julia Akabil road under conversion of 1000 nos. of SPT bridges to RCC bridges for the year 2017-18, Package no. BR-1000/LAC-71/075 (L=2x16.5m) |
203.824 |
CE/STBR/II/76/2017-18/5 Dtd.10/05/18 |
90% |
Work in Progress |
|
2 |
Construction of RCC BR. No. 1/1 over River Sopai on Panbari Garden road under conversion of 1000 nos. of SPT bridges to RCC bridges for the year 2017-18, Package no. BR-1000/LAC-71/076 (L=2x16.5m) |
183.90 |
CE/STBR/II/77/17-18/8 Dtd. 14/06/2018 |
90% |
Work in Progress |
|
3 |
Construction of RCC Bridge No 1/1 over River Sri Sri on the Road from Dumduma Boro Academy to Da Gaon under Conversion of 1000 Nos of SPT Bridges into RCC Bridges for the year 2017-18. (Pkg. No.BR-1000/LAC-72/77) |
184.712 |
CE/STBR/II/78/17-18/5 Dtd. 05/03/2018 |
97% |
Work in Progress |
Name of Division:- Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli |
|||||
Sl.No |
Name of Work |
Name of contractor |
Contract amount |
Physical progress |
Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
Annual Plan-SCSP |
|||||
1 |
Improvement of Road from Katanala Village to Da Garoimari Madhavdev L.P. School including the construction of RCC Bridge No 10/1 (2x24.75 = 49.50 RM) over Katanallajan and RCC Bridge No 5/1 (2x16.5 = 33RM) over Belsirijan via Bachasimalu under SPA for the year 2013-14 |
M/S Tribeni Construction Ltd. |
1551.797 |
100% |
Work Completed |
2 |
Improvement of Road from Dheraimajuli to Goruduba PWD Road including Conversion of SPT Bridge No 4/3 over river Belsiri under SPA for the year 2013-14 |
M/S Prabhu Agarwalla |
1418.160 |
100% |
Work Completed |
3 |
Mt. & BT of Road from NH-52 Bhotpara (Near Govt. Saw Mill) via Polash Basti M.E. School to Joy Nagar Bhangamandir Mt. & Bt Road under SPA for the year 2012-13 (Group-II) |
M/S J.J. Associates |
413.640 |
100% |
Work Completed |
State Govt. Sponsored Schemes |
|||||
Asom Darshan |
|||||
Dist : SONITPUR |
|||||
Name of Division:- Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli |
|||||
Sl.No |
Name of Work |
Name of contractor |
Contract amount Rs in L |
Physical progress |
Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
Asom Darshan for the year 2019-20 |
|||||
1 |
Improvement of approach road of Kalia Thakur Satra at Rowmari, Dhekiajuli under Assam Darshan for the year 2019-20 (Improving infrastructure in religious places. L = 0.10Km |
Ratna Newar |
15.880 |
30% |
Work in progress |
2 |
Improvement of approach road of Dhireswar Shivalaya at Kamar Chuburi, Thelamora under Assam Darshan for the year 2019-20 (Improving infrastructure in religious places.L = 0.130Km |
Chandi Das Saha |
6.50 |
100% |
Work completed |
3 |
Improvement of approach road of Adivasi Gram Than at Patidoi Bherala, Thelamora under Assam Darshan for the year 2019-20 (Improving infrastructure in religious places. L= 0.220 |
Hara Jyoti Talukder |
24.02 |
60% |
Work in progress |
4 |
Improvement of approach road of Dolpara Kochgaon Namghar at Thelamora under Assam Darshan for the year 2019-20 (Improving infrastructure in religious places.L = 0.020Km |
Chandi Das Saha |
6.60 |
100% |
Work completed |
5 |
Improvement of approach road of Mahamuni Mandir at Amtol, Bheragaon, Dhekiajuli under Assam Darshan for the year 2019-20 (Improving infrastructure in religious places.L=0.300 Km |
Naba Nath |
|
15% |
Under tender process |
6 |
Improvement of approach road of Raghunath Namghar at Panbari, Dhekiajuli under Assam Darshan for the year 2019-20 (Improving infrastructure in religious places.L = 0.02Km |
Mandeep Singh |
12.09 |
70% |
Work in progress |
7 |
Improvement of approach road of Raghunath Satra at Rowmari under Assam Darshan for the year 2019-20 (Improving infrastructure in religious places L= 0.045 Km |
Mandeep Singh |
12.5 |
25% |
Work in progress |
8 |
Improvement of approach road of Raghunath Namghar at Ghagra, Dhekiajuli under Assam Darshan for the year 2019-20 (Improving infrastructure in religious places.L=0.120 Km |
Kaju Deep |
16.19 |
30% |
Work in progress |
9 |
Improvement & upgradation of basic infrastructure, key infrastructure and connectivity of Goga Namghar, Rangamati, Bihaguri in Sonitpur District under Assam Darshan scheme for the year 2019-20 in Barchalla LAC.L = 0.545Km |
Sri Arun Kalita |
44.99 |
100% |
Work completed |
10 |
Improvement & upgradation of basic infrastructure, key infrastructure and connectivity of Bhangamandir Shiv Temple in Sonitpur District under Assam Darshan scheme for the year 2019-20 in Barchalla LAC under PWD, Sonitpur Rural Road Division, Biswanath Chariali(Package No. TRC/SOPD-G/AD/04)L = 1.00Km |
Rinku Nath |
96.1 |
60% |
Work in progress |
11 |
Improvement & upgradation of basic infrastructure and connectivity to Kalia Gokhai Than in Sonitpur District under Assam Darshan scheme for the year 2019-20 (Package No. TRC/SOPD-G/RE/10)L = 0.80Km |
Pabitra Kumar Boro |
56.3 |
15% |
Work in progress |
12 |
Improvement of approach road of Kalia Gohain satra at Naharbari, Dhekiajuli under Assam Darshan scheme for the year 2019-20 (Improving Infrastructure in reloigious places) (L=1.00Km) (Package No. TRC/SOPD-G/AD/12) |
Suraj Kumar Basumatary |
89.75 |
100% |
Work completed |
State Govt. Sponsored Schemes |
||||||
STATE OWN PRIORITY DEVELOPMENT SOPD - FDR FOR 2019-20 |
||||||
Dist : SONITPUR |
||||||
Name of Division:- Barchalla & Dhekiajuli Territorial Road Division, Dhekiajuli |
||||||
Sl.No |
Name of Work |
Name of contractor |
Contract amount Rs in L |
Physical progress |
Remarks |
|
1 |
2 |
6 |
7 |
9 |
11 |
|
1 |
Re-construction of culvert No.14/1 on Thelamora Missamari Road under SOPD FDR for the year 2019-20 (Dhekiajuli LAC) |
Geremcha Basumatary |
13.790 |
100% |
Work Completed |
|
2 |
Re-construction of culvert No.1/1 on Surjyapur No.2 to NH 52 Road under SOPD FDR for the year 2019-20(Dhekiajuli LAC) |
Geremcha Basumatary |
2.813 |
100% |
Work Completed |
|
3 |
Re-construction of Bridge Approaches of RCC Br. No. 1/1 on Jangalbasti Road under SOPD FDR for the year 2019-20 (Dhekiajuli LAC) |
Geremcha Basumatary |
15.147 |
100% |
Work Completed |
|
4 |
Re-construction of Bridge Approaches of RCC Br. No. 6/1 on107th Km to Belsiri Rly Station Road under SOPD FDR for the year 2019-20 (Dhekiajuli LAC) |
Geremcha Basumatary |
1.196 |
100% |
Work Completed |
|
5 |
Re-construction of Bridge Approaches of RCC Br. No. 4/1 on Balijan Kachari to Nichalamari Road under SOPD FDR for the year 2019-20 (Barchalla LAC) |
Chinmoy Bora |
12.146 |
100% |
Work Completed |
|
6 |
Re-construction of Bridge Approaches of RCC Br. No. 12/1 on NH-52 to Bhanga Mandir Road under SOPD FDR for the year 2019-20 (Barchalla LAC) |
Tapan Ch. Deka |
16.938 |
100% |
Work Completed |
|
7 |
Re-construction of Bridge Approaches of RCC Br. No. 13/1 on NH-52 to Bhanga Mandir Road under SOPD FDR for the year 2019-20 (Barchalla LAC) |
Kumar Ravi Jaiswal |
20.082 |
100% |
Work Completed |
|
8 |
Re-construction of work on Bhalukdhora to Singri PWD Road(including CD works) under SOPD FDR for the year 2019-20 (Barchalla LAC) |
M/S Amina Enterprise |
17.22 |
60% |
Work in progress |
|
9 |
Re-construction of Singri Chitalmari Road under SOPD FDR for the year 2019-20 (Barchalla LAC) |
Rajib Rabha |
27.630 |
85% |
Work in progress |
|
10 |
Reconstruction of Br.Aproaches RCC Br. No 2/1 on Hirajuli TE No 3 to Garjuli Road under SOPD-FDR for the year 2019-20( Dhekiajuli LAC) |
M/S MAA Construction |
65.282 |
85% |
Work in progress |
|